Project Name:  A404M Maidenhead

Client:   Birse Civils

Description: 

 
Liaising with Network Rail & Highways Agency 
Working within tight programme constraints
Weekend possessions and engineering hours
Working with the client on alternative design and construction methods
Carrying out works without causing disruption to local train services and public highways

The challenge of this job was that the bridge had to be demolished and replaced whilst staying open for traffic ,with the added complication of a four-line railway below. This was achieved by demolishing and rebuilding the bridge in sections which ensured that four lanes of traffic could still flow at all times.


Works carried out include :